This article is part of a series: Navigate to series page
In Part 3a, I started the Azure Local 2610 post-deployment Arc Gateway workflow. The portal job did not reach a clean success state. It stayed in progress, and some steps later showed as cancelled.
That did not match what I found on the cluster. The local Azure Local action plan had completed successfully, the hosts were using the gateway, and proxy logs showed actual gateway traffic. I investigated the discrepancy between the local result and Azure’s job record. I found why the cloud operation was cancelled, but not why it stopped receiving progress updates or how to repair its status.
HINT A successful local action and a stale cloud job are different pieces of evidence. Do not treat either one alone as proof that the whole operation is healthy.
Problem and symptoms
The Configure Arc gateway job remained Deployment In Progress in the portal well after I had started it. Later, some individual steps showed Cancelled, while the overall job still appeared to be in progress.
On both Azure Local hosts, azcmagent show reported Connected, with the local HTTPS proxy and the gateway URL configured. The agent checks reached their tested endpoints, and arcproxy.log contained successful gateway connections. The Windows proxy settings and Azure Arc resource bridge proxy settings also reflected the configured proxy paths.
The local ECE action plan provided the clearest completion evidence. Its status was Completed, and its progress XML recorded success for proxy validation, agent-version validation, both hosts, Azure Arc resource bridge convergence, the ECE sticky proxy update, and the overall action.
The portal state was not just a stale browser display. A read-only query of the Azure job resource showed provisioningState as Failed, while the reported execution status remained DeploymentInProgress with InProgress steps. The cluster resource separately reported that it was connected. The job resource and the local action plan disagreed.
What the Activity Log identified
The Azure Activity Log showed the terminal error for the original operation:
ResourceOperationFailure
DeployClusterOperationFailed
CleanStuckJobInProgress
No Updates were received from the HCI device in the last 60 minutes, so marking
ClusterJob_Deploy Operation cancelled. Please contact Microsoft support for
further details.
The local action plan finished successfully at about 18:52 UTC on 31 October. The last accepted job update visible in the Activity Log was about three minutes before that. Azure recorded the cancellation roughly 57 minutes after the local action had finished, after the 60-minute no-update interval.
This explains why the cloud operation was cancelled. It does not explain why Azure stopped receiving device updates before the local completion was reported. The Activity Log did not include the request bodies needed to determine which progress values had been sent, and I did not find a verified reporting log or a cause for the missing final status.
How I investigated the mismatch
1. Check the local action plan
From an elevated Azure Local PowerShell session, find the action plan for the operation and inspect its progress XML:
Get-ActionPlanInstances |
Sort-Object StartDateTime -Descending |
Select-Object -First 20 |
Format-Table InstanceID, ActionPlanName, ActionTypeName,
Status, StartDateTime, EndDateTime -AutoSize -Wrap
$job = Get-ActionPlanInstance -ActionPlanInstanceID '<action-plan-instance-id>'
$job | Format-List *
$job.ProgressAsXml
Use the action-plan instance that matches the gateway operation and its timestamp. In my case, the XML recorded success for every listed step, including the final ECE sticky proxy update. A successful task entry is evidence of that task’s recorded outcome; it is not an independent read-back of every persisted setting.
2. Verify the configured path separately
Check the Connected Machine agent, proxy configuration on each host, the resource bridge proxy, and fresh proxy-log entries. The checks in Part 3c cover those layers.
My host checks and logs showed that the local configuration was in use. They did not show that every destination used the gateway: some traffic followed direct or bypass paths, as expected. Keep those paths distinct when interpreting logs.
3. Read the cloud job and its Activity Log
Use an authenticated Azure session to read the exact job resource and inspect the Activity Log for the original operation. I widened the Activity Log query to the resource group so it included events for both the cluster and its child job.
The job response showed conflicting provisioning and execution states. The Activity Log then exposed the 60-minute no-update cancellation. An accepted job update is not proof of the progress payload it contained, and a missing event by itself is not proof that no update was sent.
What did not fix it
Restarting the clustered Cloud Management resource brought it back online, but the job state did not change. I also updated the Azure Local instance and rebooted both nodes; the user-reported job state remained stuck afterward.
I did not find a supported command to republish the completed local action as a successful Azure job. I did not rerun the enablement, modify ECE state, or manually change the Azure job status. Those actions could hide evidence or create a second problem without addressing the missing completion report.
Recommendation
I would preserve the local action-plan XML, the exact Azure job response, and the Activity Log entries, then take them to Microsoft support. The cancellation message identifies a progress timeout; the underlying reporting failure and a verified repair remain unknown.
Keep the existing firewall allowlist in place while investigating. Do not harden egress based on host proxy settings alone, and do not call the operation fully resolved while the cloud job still reports failure. Once the job discrepancy is addressed, use Part 3c to validate the infrastructure and traffic paths before reducing any firewall rules.